Rawat Steel Works

Highway Bridge Girders, Punjab

Categories
Client: Punjab Highways Department
Project Start: 18/09/2024
Scope: 420 tonnes plate girders
Contractor: Rawat Steel Works
Location: Chakwal, Punjab
Value: PKR 190 million
logo-lv1
Let’s Start Work Together
+92 51 459 2200
Plot 21, Rawat Industrial Estate, GT Road, Rawat, Rawalpindi
sales@rawatsteel.saadtariq.app
Mon - Sat: 8.00am - 6.00pm

About Project

Fabrication of welded plate girders for a 3-span highway bridge.

The girders were cut, welded and painted in our facility, then transported to site in sections.

Our Client’s Challenge

The girders required full-penetration welds, ultrasonic testing and strict camber tolerances.

Our Approach And Solution

We used CNC-cut plates, qualified welding procedures and third-party ultrasonic testing on every girder.

Outcome

All girders passed inspection on the first attempt.

The bridge opened to traffic in March 2025.

Connect With Rawat Steel.

Send us a message to have all your questions answered about Rawat Steel products and services